Morris Bridge Road Repaving from Davis Road to Fletcher Avenue 439532-1-52-01
Project Details
Work Type | Repaving |
---|---|
Phase | Construction |
Limits | from Davis Road to Fletcher Avenue |
Project Start | March 2021 |
Length | 2.2 miles |
City | |
County | |
Construction Cost | $4.5 million |
Estimated Completion | Late 2022 |
Contractor | Ranger Construction Industries, Inc. |
About
This project is repaving Morris Bridge Road between Davis Road and Fletcher Avenue in Temple Terrace.
Other improvements include:
- adding a six-foot sidewalk along the west side of the road between Davis Road and Fowler Avenue
- widening the roadway between Fowler Avenue and Fletcher Avenue to provide five-foot paved shoulders on both sides of the road
- adding an eight-foot-wide shared-use path between Fisherman's Point and 127th Avenue
- eliminating the gaps in the existing sidewalk between 127th Avenue and Fletcher Avenue
Construction is expected to finish by late 2022.
Project numbers 439532-1 and 439532-2 were combined into a single construction contract. All updates for both project numbers will be posted on this page.
View Factsheet
Contact Information
Construction Manager |
---|
Alene Harris
813-612-3200
Alene.Harris@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Lane Closures
- There are no lane closures at this time.