Project Details
Work Type Repaving ( High Friction Surface Treatment)
Phase Construction
Limits from W. of Lagoon St. to Sheldon Road
Project Start August 31, 2020
Length .2 miles
City
County
Road
Construction Cost $607,103
Estimated Completion Early 2021
Contractor Hubbard Construction Company
About

This project involves removing the existing top layer of asphalt and replacing it with a high friction surface treatment on the eastbound lanes of Hillsborough Avenue to correct rutting.

Crosswalks will also be added to the intersections of Lagoon Street and Sheldon Road.

Construction is expected to finish in early 2021.

View Factsheet
Contact Information
Construction Manager
Salem Dhouib
813-612-3200
Salem.Dhouib@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kris.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.