Project Details
Work Type Repaving
Phase Construction
Limits from north of Fletcher Avenue to south of Van Dyke Road
Project Start Summer 2022
Length 4.296 miles
City
County
Road
Construction Cost $8.4 million
Estimated Completion Spring 2023
Contractor Preferred Materials, Inc.
About

This project will repave Dale Mabry Highway between Fletcher Avenue and Van Dyke Road.

The traffic signal at Bearss Avenue will be replaced as well.

Construction is anticipated to begin in the summer of 2022 and be complete in the spring of 2023.

View Factsheet