I-75 Widening from the Tampa Bypass Canal to Fowler Avenue 445317-1-52-01, 445317-2-52-01
Project Details
Work Type | Add Lanes and Reconstruct |
---|---|
Phase | Construction |
Limits | from north of Broadway Ave to south of SR 582/Fowler Ave |
Project Start | December 9, 2024 |
Length | 1.3 miles |
City | |
County | |
Road | |
Construction Cost | $125.6 million (combined FPN: 443630-2) |
Estimated Completion | 2028 |
Contractor | Webber, LLC |
About
This project will add a lane in both the southbound and northbound direction of I-75 from south of the Tampa Bypass Canal to south of Fowler Avenue in Hillsborough County.
The bridges over the Tampa Bypass Canal and Harney Road will also be widened, and the bridge structures over US 301 will be replaced.
Construction is estimated to finish during 2028.
This project is being constructed in conjunction with the pavement rehabilitation of I-75 from Broadway Avenue to Fowler Avenue in Tampa (FPN: 443630-2-52-01).
Contact Information
Project Information |
---|
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
-
I-75 from Fowler Avenue to SR 574 (Dr. Martin Luther King Jr. Boulevard)
Lane closures (southbound): Monday, May 18 through Friday, May 23 nights from 10 p.m. to 5 a.m. (lane closure will be on going through July 3rd, Monday through Friday)