I-75 Widening from the Tampa Bypass Canal to Fowler Avenue 445317-1-52-01, 445317-2-52-01
Project Details
| Work Type | Add Lanes and Reconstruct |
|---|---|
| Phase | Construction |
| Limits | from north of Broadway Ave to south of SR 582/Fowler Ave |
| Project Start | December 9, 2024 |
| Length | 1.3 miles |
| City | |
| County | |
| Road | |
| Construction Cost | $125.6 million (combined FPN: 443630-2) |
| Estimated Completion | 2028 |
| Contractor | Webber, LLC |
About
This project will add a lane in both the southbound and northbound direction of I-75 from south of the Tampa Bypass Canal to south of Fowler Avenue in Hillsborough County.
The bridges over the Tampa Bypass Canal and Harney Road will also be widened, and the bridge structures over US 301 will be replaced.
Construction is estimated to finish during 2028.
This project is being constructed in conjunction with the pavement rehabilitation of I-75 from Broadway Avenue to Fowler Avenue in Tampa (FPN: 443630-2-52-01).
Contact Information
| Project Information |
|---|
|
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
|
| Media Contact |
|
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
-
I-75 from Tampa Bypass Canal to Fowler Avenue
Lane closure (northbound): Monday, October 20 through Saturday, October 25 from 6 a.m. to 6 p.m.
I-75 from SR 574 (Dr. Martin Luther King Jr. Boulevard) to Fowler Avenue
Lane closures: Sunday, October 19 through Friday, October 24 nights from 10 p.m. to 5 a.m. (lane closures to continue through October 31 Monday through Friday) -
I-75 from the Tampa Bypass Canal to Fowler Avenue
Lane (shoulder) closures: 24 hours per day of shoulder closure through Friday, November 7, 2025. -
I-75 from Fowler Avenue to SR 574 (Dr. Martin Luther King Jr. Boulevard)
Lane closures: Sunday, August 24 through Thursday, August 28 nights from 10 p.m. to 5 a.m. (Lane closure to continue through October 31, Monday through Friday)