I-275 Capacity Improvements from north of I-4 to north Hillsborough Avenue
- Project ID
- 431821-2-52-01, 443770-1-52-01
Project Details
- Work Type
- Capacity Improvements
- Phase
- Completed
- Limits
- from north of I-4 to north of US 92 (Hillsborough Ave)
- Length
- 2.5 miles
- City
- County
- Road
About
All construction activities associated with this project were completed on Wednesday, March 5, 2025.
Click to view the I-275 Virtual Open House Tour
The $96.7 million capacity improvement project added one lane in each direction to I-275 from north of I-4 to north of Hillsborough Avenue (US 92) using the existing right-of-way.
Other improvements: constructed noise barrier walls along the corridor, installed fencing and Intelligent Transportation System (ITS) devices, and reconstructed the overpasses between Floribraska Avenue and Hillsborough Avenue.
*Construction cost included original construction contract amount plus approved contract changes. It did not include inspection oversight.
Contact Information
-
Media Contact
- Name:
- Kris Carson
- Phone:
- 813-975-6060