This project has been completed. The information on this webpage is archived for reference and research purposes.

Project Details

Work Type
Capacity Improvements
Phase
Completed
Limits
from north of I-4 to north of US 92 (Hillsborough Ave)
Length
2.5 miles
City
County
Road

About

All construction activities associated with this project were completed on Wednesday, March 5, 2025. 

Click to view the I-275 Virtual Open House Tour

The $96.7 million capacity improvement project added one lane in each direction to I-275 from north of I-4 to north of Hillsborough Avenue (US 92) using the existing right-of-way.

Other improvements: constructed noise barrier walls along the corridor, installed fencing and Intelligent Transportation System (ITS) devices, and reconstructed the overpasses between Floribraska Avenue and Hillsborough Avenue. 

*Construction cost included original construction contract amount plus approved contract changes. It did not include inspection oversight.

View Factsheet The link target will open in a new tab.