I-275 Capacity Improvements from north of I-4 to north US 92 (Hillsborough Ave) 431821-2-52-01
Project Details
Work Type | Capacity Improvements |
---|---|
Phase | Construction |
Limits | from north of I-4 to north of US 92 (Hillsborough Ave) |
Project Start | October 25, 2021 |
Length | 2.5 miles |
City | |
County | |
Road | |
Construction Cost | $85.3 million |
Estimated Completion | Early 2026 |
Contractor | Lane Construction Corporation |
About
Click on link to View the I-275 Virtual Open House Tour
The department's contractor, Lane Construction, has begun construction activities as part of the I-275 Capacity Improvement project in Tampa.
The $85.3 million project is adding one lane in each direction to I-275 from north of I-4 to north of Hillsborough Avenue (US 92) using the department’s existing right-of-way.
Other improvements include constructing noise barrier walls along most of the corridor, installing fencing and Intelligent Transportation System (ITS) devices, and reconstructing the overpasses at Floribraska Avenue, Lake Avenue, Martin Luther King Jr. Boulevard, Chelsea Street, Osborne Avenue, and Hillsborough Avenue providing wider sidewalks and bright underdeck lighting.
Construction activities are taking place during the daytime and nighttime hours. Work requiring lane closures will occur at night between 9 p.m. and 6:30 a.m. Occasionally, interstate ramps may close at night between 11 p.m. and 5 a.m. for overhead signage and underpass work. Advanced warning signs and electronic message boards will assist motorists traveling through the area.
Due to high traffic volumes, some of the work will be done overnight. To construct the project, heavy machinery and lighting will be used during daytime and nighttime hours. Concrete and asphalt work may produce noise, vibration, and lighting impacts.
Construction activities are expected to finish in early 2026.
To receive construction updates and traffic alerts via email, be sure to subscribe above.
Projects (431821-2 and 443770-1) are now one single construction project.
Contact Information
Construction Manager |
---|
Melissa Chin
813-975-3573
Melissa.Chin@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Lane Closures
-
I-275 northbound and southbound from north of I-4 interchange to north of Hillsborough Avenue
Lane closures: Sunday, May 22 through Thursday, May 26 from 9 p.m. to 6 a.m.