Project Details
Work Type Widening
Phase Construction
Limits from north of I-4 to north of US 92/Hillsborough Ave
Project Start Fall 2021
Length 2.5 miles
City
County
Road
Construction Cost $85.3 million
Estimated Completion Early 2026
Contractor Lane Construction Corporation
About

This project will add one general use lane in each direction on I-275 between I-4 and US 92 (Hillsborough Ave.) in Tampa.

Noise barrier and intelligent transportation system components will also be added.  Underpasses in this area will also have pedestrian lighting and aesthetic enhancements added.  

Construction is anticipated to begin in the fall of 2021 and be complete in early 2026. 

This project has been combined with 443770-1 into a single construction project. 

View Factsheet
Contact Information
Construction Manager
Tom Lay
813-975-3554
tom.lay@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.