Project Details
Work Type Safety Improvements
Phase Construction
Limits between Central Ave and 56th Street
Project Start January 2021
City
County
Road
Construction Cost $196,664.04
Estimated Completion Summer 2021
Contractor Ajax Paving Industries of Florida
About

The Florida Department of Transportation's contractor, Ajax Paving Industries of Florida, is adding a High-Intensity Activated Crosswalk (HAWK) in the median with pedestrian-activated lighting along Hillsborough Avenue between east of Central Avenue and 56th Street in Tampa.  

Construction is expected to finish summer of 2021. 

View Factsheet
Contact Information
Construction Manager
Randall Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.