Project Details
Work Type Intersection Improvements
Phase Construction
Limits 15th St, 22nd St, University Collection, 30th St/Bruce B. Downs and 56th St
Project Start July 12, 2021
City
County
Road
Construction Cost $2.1 million
Estimated Completion Summer 2022
Contractor Ajax Paving Industries of Florida, LLC
About

This design-build improvement project is upgrading multiple intersections along Fowler Avenue at 15th Street, 22nd Street, University Collection, 30th Street/Bruce B. Downs Boulevard and 56th Street in Tampa and Temple Terrace.

Upgrades include:

  • modifying curbs, pedestrian islands, and medians
  • installing new pedestrian signals, ramps, and intersection lighting
  • adding truck aprons (see posted images)  

What are truck aprons and why are they colored red? Truck aprons slow down vehicles before turning onto a roadway and provide a safer environment for pedestrians and bicyclists. They are designed to allow the trailer of commercial vehicles to drive over the apron when making a right turn at an intersection. Truck aprons are colored red to provide enhanced visibility.

Construction is estimated to finish summer of 2022.  

View Factsheet
Contact Information
Construction Manager
Hamid Jafarian
813-612-3200
Hamid.Jafarian@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • SR 582 (Fowler Avenue) at 56th Street (eastbound and westbound)
    Lane closures: Sunday, May 22 through Thursday, May 26 from 8:30 p.m. to 6 a.m.

Project Images
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (March 2022)
SR 582 (Fowler Avenue) Intersection Improvements (Multiple Locations)