Project Details
Work Type Highway Lighting
Phase Construction
Limits from 56th St. to I-4
Project Start Fall 2021
Length 1.5 miles
City
County
Road
Construction Cost $755,204.35
Estimated Completion Summer 2022
Contractor Highway Safety Devices, Inc.
About

This project will replace existing and install new highway lighting along the US 92 (Hillsborough Avenue) corridor between 56th Street and I-4 in Hillsborough County.  

Construction is to begin in the fall of 2021 and finish summer of 2022. 