SR 589 (Veterans Expressway) Repaving Exit Ramps to Independence Parkway 254677-5-10
Project Details
Work Type | Safety Improvements |
---|---|
Phase | Completed |
Limits | at Independence Parkway |
City | |
County | |
Road |
About
As of January 19, 2022, all work associated with this project has been completed.
This design-build project is replacing the top layer of asphalt with a high friction treatment to improve exit ramp surface from SR 589 (Veterans Expressway) onto Independence Parkway in Hillsborough County.
Status: Construction has begun and is expected to finish during late 2021
This project has been combined with 254677-5-3
View Factsheet
Contact Information
Media Contact |
---|
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.