Project Details
Work Type Highway Lighting upgrades
Phase Construction
Limits North of Hampton Oaks Parkway to West of Jackson Road on US 301 (SR 41)
Project Start Fall 2022
Length 4.5 miles
City
County
Road
Construction Cost $801,180
Estimated Completion Early 2023
Contractor Transportation Systems Inc.
About

This project will replace the existing highway lighting bulbs on US 301 between Hampton Oaks Parkway and Jackson Road in Temple Terrace. The new bulbs will be LED. 

Construction is anticipated to begin in the fall of 2022 and be complete in early 2023.

View Factsheet
Contact Information
Construction Manager
Farhad Zafaranian
813-612-3200
Farhad.Zafaranian@dot.state.fl.us
Media Contact
Kris Carson
(813) 975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.