Project Details
Work Type Signal and Pedestrian Improvements
Phase Construction
Limits US 41 (21st/22nd Streets) at Selmon Expressway
Project Start April 3, 2023
City
County
Road
Construction Cost $1.2 million
Estimated Completion Spring 2024
Contractor Traffic Control Devices, Inc.
About

The Florida Department of Transportation's contractor, Traffic Control Devices, Inc., made safety improvements to the intersection of US 41 (21st Street/22nd Street) at Selmon Expressway in Tampa.     

Improvements include:
- installation of new traffic signals
- installation of mid-block pedestrian crosswalks with raised traffic separators and pedestrian refuges
- adding signage and necessary pavement markings 

This project is expected to finish in the spring of 2024.

View Factsheet
Contact Information
Project Information
Devin Wood
813-612-3212
Devin.Wood@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.