Work Type Arterial Traffic Management System and Intelligent Transportation System Upgrades
Phase Construction
Limits From Airport Service Rd to Dale Mabry Hwy
Project Start March 20, 2023
Length 3.2 miles
City
County
Road
Construction Cost $29.2 million
Estimated Completion Early 2025
Contractor Highway Safety Device Inc.
About

This design build project will install fiber optic communications tools and hardware along Boy Scout Blvd between Airport Service Rd and Dale Mabry Highway to assist with traffic management in Tampa.

Construction activities are expected to finish early 2025.

View Factsheet
Contact Information
Project Information
Maricelle Venegas
813-975-6204
roadwork@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.
Project Images
SR 616 (Boy Scout Blvd) Arterial Traffic Management System Upgrades from Airport Service Rd to Dale Mabry Hwy (Jan 2024)
SR 616 (Boy Scout Blvd) Arterial Traffic Management System Upgrades from Airport Service Rd to Dale Mabry Hwy
SR 616 (Boy Scout Blvd) Arterial Traffic Management System Upgrades from Airport Service Rd to Dale Mabry Hwy (January 2024)