Work Type Truck Parking Facility
Phase Construction
Project Start September 20, 2025
City
County
Road
Construction Cost $29.4 million
Estimated Completion Late 2026
Contractor Ajax Paving Industries of Florida, LLC
About

The FDOT is constructing the new I-4 Truck Parking Facility, along with making roadway and pedestrian improvements to County Line Road over the interstate in Hillsborough County.

The new I-4 Truck Parking Facility is being built on a 49-acre FDOT-owned site and will provide 160 truck parking spaces.

The new facility will be integrated into Florida’s Truck Parking Availability System (TPAS) to provide drivers with real-time parking availability information via a mobile application and dynamic roadside signs.

The project includes other infrastructure improvements for trucks accessing the I-4 Truck Parking Facility, as well as traffic entering and exiting I-4 at County Line Road.

Improvements include:

  • Replacing the traffic signal and providing dual right and left turn lanes from the eastbound I-4 exit ramp onto County Line Road.
  • Adding a traffic signal and providing dual right and left turn lanes from the westbound I-4 exit ramp onto County Line Road.
  • Reducing the radii and adding truck aprons to accommodate trucks.
  • Modifying traffic signals and reconfiguring travel lanes along County Line Road to reduce truck delays and improve mobility.
  • Installing new signage and pavement markings, highway lighting, and ITS systems.

Construction activities are expected to finish during late 2026.

************************************************************************

What is design-build? Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT (or any owner) to fully design and construct a project.  The contract work covers from initial design through construction completion.  This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously. 

View Factsheet
Contact Information
Project Information
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • County Line Roadfrom Swindell Road to South Frontage Road
    Lane closures (southbound): Sunday, June 21 through Thursday, July 2 nights from 8 p.m. to 6 a.m.

Project Files
Project Images
Image of drainage structures under County Line Road near ramps to I-4 (Photo June 2026)
Image of subgrade work along I-4 ramps from County Line Road looking westbound (Photo June 2026)
Image of subgrade work along I-4 ramps from County Line Road looking westbound (Photo June 2026)
Image of new concrete curb work and sidewalk on County Line Road looking south (Photo June 2026)
Image of concrete curb work on County Line Road approaching ramps to I-4 (Photo June 2026)
Image of concrete curb work on County Line Road looking south (Photo June 2026)
I-4 Truck Parking Facility (May 2026)
I-4 Truck Parking Facility (May 2026)
I-4 Truck Parking Facility (May 2026)
I-4 Truck Parking Facility (December 2025)
I-4 Truck Parking Facility (December 2025)
I-4 Truck Parking Facility (December 2025)
I-4 Truck Parking Facility (December 2025)
I-4 Truck Parking Facility (November 2025)
I-4 Truck Parking Facility (November 2025)
I-4 Truck Parking Facility (November 2025)
I-4 Truck Parking Facility (November 2025)