Work Type Safety Improvements
Phase Construction
Limits Fletcher Avenue and I-75 SB Exit Ramp
Project Start Fall 2024
City
County
Road
Construction Cost $900,000
Estimated Completion Spring 2025
Contractor Cone & Graham, Inc.
About

The Florida Department of Transportation's Design-Build firm, Cone & Graham, Inc., is installing a new traffic signal at the intersection of Fletcher Avenue (CR 582A) and the I-75 southbound ramp (Exit 266) in Hillsborough County.

Other safety and operational improvements include roadway resurfacing, installing sidewalk, and extending the westbound left-turn lane from Fletcher Avenue onto the I-75 southbound entrance ramp.  

Construction is expected to begin in fall 2024 and be complete in spring 2025. 

View Factsheet
Contact Information
Project Information
Maddie Pfingsten
727-575-8334
roadwork@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.