SR 39 (Alexander Street) New Traffic Signal at Mud Lake Road 254677-5-38
Project Details
Work Type | Safety Improvements |
---|---|
Phase | Construction |
Limits | at Mud Lake Road |
Project Start | August 23, 2023 |
City | |
County | |
Road | |
Construction Cost | $600,000 |
Estimated Completion | Early 2024 |
Contractor | Cone & Graham, Inc. |
About
The Florida Department of Transportation's Design-Build Firm, Cone & Graham, Inc., is adding a new traffic signal at SR 39 (Alexander Street) and Mud Lake Road in Hillsborough County.
Other safety and operational improvements include sidewalk installation, and addition of pedestrian signals and crosswalks.
Construction activities are underway and expected to be complete in early 2024.
View Factsheet
Contact Information
Project Information |
---|
Maddie Pfingsten
727-575-8334
roadwork@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
-
SR 39 (Alexander Street) at Mud Lake Road
Lane closures: Monday, April 22 through Friday, April 26 from 7 a.m. to 5 p.m.