SR 582 (Fowler Ave) Repaving from Bruce B Downs Blvd to Riverhills Dr 446270-1-52-01
Project Details
Work Type | Repaving |
---|---|
Phase | Construction |
Limits | Bruce B Downs Blvd to Riverhills Dr |
Project Start | Late 2024 |
Length | 3.5 miles |
City | |
County | |
Road | |
Construction Cost | $8.1 million |
Estimated Completion | Early 2026 |
Contractor | Preferred Materials, Inc. |
About
This project will repave Fowler Avenue (SR 582) from Bruce B Down Boulevard to Riverhills Drive in Temple Terrace.
Additional improvements include minor drainage work, new traffic signal at 52nd Street, highway lighting retrofitting, updating ADA features, and performing general safety modification work.
Construction is anticipated to begin during late 2024.
Contact Information
Project Information |
---|
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.