As of October 17, 2026, all construction activities associated with this $2.1 million project have been completed.

Project interchange improvements included the following:

  • Re-striped the existing pavement to provide a 2-lane northbound I-75 exit ramp to SR 52.
  • Provided a 2-lane ramp from westbound SR 52 to the southbound I-75 entrance ramp.
  • Provided dual left turn lanes from eastbound SR 52 to the entrance ramp onto northbound I-75.
  • Provided two receiving lanes on the northbound I-75 entrance ramp.
  • Reconfigured the existing lanes on westbound SR 52 from Pasco Road to I-75 accordingly.