Project Details

Work Type
Repaving/Median Modifications
Phase
Construction
Limits
from Buckingham Place to Lithia Pinecrest Road
Project Start
March 13, 2026
Length
.921 Miles
City
County
Road
Construction Cost
$3.7 million
Estimated Completion
Fall 2026
Contractor
Hubbard Construction Company

About

This project is repaving the existing travel lanes along SR 60 from Buckingham Place to Lithia Pinecrest Road in Hillsborough County.

Additional improvements include:

  • modifying turning movements
  • making repairs to damaged sidewalk
  • adding pedestrian lighting to intersection

Construction activities are taking place during daytime and nighttime hours. Work requiring lane closures will occur nightly from 9 p.m. to 6 a.m.  

Access to driveways, sidewalks, and side streets to be maintained. Motorists are reminded to use caution when traveling through the work zone and remain alert for pedestrians and construction workers. 

Construction activities are expected to finish during fall of 2026.     

View Factsheet The link target will open in a new tab.

Contact Information

Closures

  • SR 60 from Buckingham Place to Lithia Pinecrest Road
    Lane closures: Sunday, October 4 through Thursday, October 8, nights from 8 p.m. to 6 a.m.