SR 60 Repaving from Buckingham Place to Lithia Pinecrest Road 441662-1-32-01
Project Details
Work Type | Repaving/Median Modifications |
---|---|
Phase | Construction |
Limits | from Buckingham Place to Lithia Pinecrest Road |
Project Start | Late 2025 |
Length | .921 Miles |
City | |
County | |
Road | |
Construction Cost | $3.7 million |
Estimated Completion | Summer 2026 |
Contractor | Hubbard Construction Company |
About
This project will repave the existing seven travel lanes along SR 60 from Buckingham Place to Lithia Pinecrest Road in Hillsborough County.
Additional improvements include:
- modifying turning movements
- making repairs to damaged sidewalk
- adding pedestrian lighting to intersection
Construction activities are expected to begin by late 2025.
View Factsheet
Contact Information
Project Information |
---|
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.