Project Details
Work Type Resurfacing
Phase Construction
Limits from the Hernando County line to US 19
Project Start October 29, 2024
Length 3.34 Miles
City
County
Road
Construction Cost $7.5 million
Estimated Completion Summer 2025
Contractor Superior Asphalt, Inc.
About

This project is repaving US 98 (W Ponce De Leon Blvd.) between the Hernando County line (west of the Suncoast Parkway) and US 19 (S Suncoast Blvd.) in Citrus County.

Construction began October 29, 2024.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • US 98from the Hernando County line to US 19
    Lane closures: Monday, February 10 through Saturday, February 15 from 7 a.m. to 8 p.m.