Project Details
Work Type Resurfacing
Phase Construction
Limits SR 56 from west of Bruce B. Downs Blvd. to east of Meadow Pointe Blvd. and Bruce B. Downs from SR 56 to SR 54
Project Start late summer / early fall
Length 7.3 Miles (both roads)
City
County
Road
Construction Cost $19.8 million
Estimated Completion fall 2027
Contractor Preferred Materials, Inc.
About

Two projects have been combined to be built under one construction contract.

The purpose of this project is to preserve and extend the life of the existing pavement through milling and resurfacing on two state roadways:

  • SR 56 from Bruce B. Downs Boulevard to Meadow Point Boulevard (3.8 miles)
  • SR 581 (Bruce B. Downs Boulevard) from SR 56 to SR 54 (3.5 miles)

This project will improve traffic flow on Meadow Pointe Boulevard near the SR 56 intersection. The work will adjust the merge area and roadway transitions to create two 12‑foot lanes that safely accommodate the added left‑turn movements at SR 56.

The project also includes intersection safety improvements at the SR 56 / Bruce B. Downs Boulevard intersection, ADA feature enhancements, minor drainage improvements, traffic signal upgrades, and overhead lighting.

Construction is anticipated to begin in late summer / early fall 2026.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.