Project Details
Work Type Safety Improvements
Phase Construction
Limits at Anclote Road/Coquina Drive
Project Start May 21, 2025
City
County
Road
Construction Cost $1.3 million
Estimated Completion Late 2026
Contractor Cone & Graham, Inc.
About

The Florida Department of Transportation's Design-Build Firm, Cone & Graham, Inc., is adding a new traffic signal at ALT US 19 (Pinellas Avenue) at Anclote Road/Coquina Drive in Pinellas County. 

Other safety and operational improvements include road resurfacing, and pedestrian and lighting improvements. 

Construction activities are expected to be complete in late 2026. 

Please click on the following link to learn more about staying safe in work zones: Work Zone Safety It's Everyone's Job

*********************************************************************************

What is design-build? Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT (or any owner) to fully design and construct a project.  The contract work covers from initial design through construction completion.  This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously. 

View Factsheet
Contact Information
Project Information
Bryce Johns
727-575-8334
Bryce.Johns@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • ALT US 19 (Pinellas Avenue) at Anclote Road/Coquina Drive 
    Lane closures: Monday, September 22 through Friday, September 26 from 8 a.m. to 6 p.m.