Pinellas County Drainage Repairs Various Locations 445830-1-52-01
Project Details
Work Type | Bridge Repair |
---|---|
Phase | Construction |
Project Start | September 16, 2024 |
Length | 6.26 |
City | |
County | |
Road | |
Construction Cost | $1.7 million |
Estimated Completion | Summer 2025 |
Contractor | M & J Construction Company |
About
This project will provide routine maintenance activities and drainage improvements to I-275, I-175 and I-375.
Construction activities are expected to complete in summer 2025.
View Factsheet
Contact Information
Project Information |
---|
Maddie Griffin
727-575-8334
roadwork@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
-
I-175 Westbound ramp to Southbound I-275
Lane closures: Wednesday, February 12 and Thursday, February 13 nights from 8 p.m. to 6 a.m.