This project has been completed. The information on this webpage is archived for reference and research purposes.
Project Details
Work Type Sidewalk
Phase Completed
Limits 1) Land O’ Lakes Blvd from north of Gator Lane to north of Causeway Blvd. and 2) SR 54 from east of Northpointe Pkwy to east of Hackberry Sq
Length 0.846 miles
City
County
Road
About

As of January 25 2026, all construction activities associated with this project have been completed.  

This project built concrete sidewalks at two locations:

  1. A 6-foot-wide sidewalk on the west side of US 41 (Land O' Lakes Boulevard) from north of Gator Lane to Sabal Palm Court.
  2. A 5-foot-wide sidewalk on the north side of SR 54 from east of Bexley Village Drive to west of Crestbend Boulevard.

The project also included new concrete driveways, drainage improvements, pavement markings, and new signs.

View Factsheet
Contact Information
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Project Images
Looking south along US 41 at new sidewalk next to Land O' Lakes High School (1-28-2026 photo)
Looking south along US 41 at new sidewalk next to Land O' Lakes High School (1-28-2026 photo)
Looking south along US 41 at new sidewalk next to Land O' Lakes High School (1-28-2026 photo)
Looking north along US 41 at new sidewalk north of Land O' Lakes High School (1-28-2026 photo)
Looking north at sidewalk construction on the west side of US 41 between Gator Lane and Causeway Blvd. (11-6-2025 photo)
Looking south at sidewalk construction on the west side of US 41 between Causeway Blvd. and Gator Lane (11-6-2025 photo)