US 301 at Wire Road -- New Traffic Signal 455145-1-52-01
Project Details
| Work Type | Traffic Signal Installation and Intersection Improvement |
|---|---|
| Phase | Construction |
| Limits | Intersection of US 301 at Wire Road |
| Project Start | May 11, 2026 |
| Length | 1,200 feet (0.23 mile) |
| City | |
| County | |
| Road | |
| Construction Cost | $1.7 million |
| Estimated Completion | Fall 2026 |
| Contractor | Cone & Graham, Inc. |
About
This project will install a new traffic signal at the US 301 / Wire Road intersection. The project will also include the construction of a new northbound left turn lane due to the high volume of U-turns. Pedestrian crosswalks and roadway lighting will also be built as part of this project.
Construction is underway as of May 11, 2026.
Contact Information
Closures
-
US 301 at Wire Road
Northbound right turn lane partial closed (but turns still available): Tuesday, June 23 from 7:30 a.m. to 5:30 p.m.
US 301 at Wire Road
Northbound right turn lane partial closed (but turns still available) and the acceleration lane from Wire Road to northbound US 301 will be closed: Thursday, June 25 and Friday, June 26 from 7:30 a.m. to 5:30 p.m. -
US 301 from Kingsmere Road to Wire Road
Southbound right lane closed around-the-clock until further notice