I-275 (Sunshine Skyway Bridge) Bridge Repair 450586-1-52-01
Project Details
| Work Type | Bridge Repair | 
|---|---|
| Phase | Construction | 
| Project Start | July 18, 2025 | 
| Length | 1.7 miles | 
| City | |
| County | |
| Road | |
| Construction Cost | $5.6 million | 
| Estimated Completion | Spring 2026 | 
| Contractor | Southern Road & Bridge, LLC | 
About
Southern Road & Bridge, LLC, on behalf of the Florida Department of Transportation is performing routine bridge repairs to the Sunshine Skyway Bridge over Tampa Bay in Pinellas County.
Construction activities are expected to be complete in spring 2026.
Please click on the following link to learn more about staying safe in work zones: Work Zone Safety It's Everyone's Job
	
	
	
	
	
	View Factsheet
	
		
								
						
						
                
                        
						
             
			
						
				
		
		
		
		
		
		
		
		
            Contact Information
| Project Information | 
|---|
| Bryce Johns 727-575-8334Bryce.Johns@dot.state.fl.us | 
| Media Contact | 
| Kris Carson 813-975-6060Kristen.Carson@dot.state.fl.us | 
Closures
- There are no closures at this time.
 FDOT Emergency Travel Alert: For information on the current situation, please visit the following
            page -
            FDOT Emergency Travel Alert: For information on the current situation, please visit the following
            page -  