Project Details
Work Type Widening
Phase Construction
Limits from W. Green Acres Street to S. Jump Court
Project Start November 7, 2016
Length 2.1 miles
City
County
Road
Construction Cost $31.8 million
About

IMPORTANT CONSTRUCTION UPDATE

Construction on this project is temporarily suspended. The original project contractor submitted a letter on July 28, 2021 informing the Florida Department of Transportation (FDOT) that it was financially unable to perform or complete the performance of the work as prime contractor, which constitutes a voluntary default by the contractor.

FDOT projects have contract bonds issued by a surety company, which is a contract requirement. The surety is in the process of contracting with a completion contractor.

A project completion date will be determined once the completion contract is awarded and a schedule is agreed to by the completion contractor and the Department.

Updates about hiring a new contractor and resuming work will be posted on this page and sent to list subscribers (click the button above this section to subscribe to the email alert list for this project).

Your patience is appreciated while the completion contractor process moves forward.

This project involves widening US 19 in Homosassa Springs from four lanes to a six-lane divided highway with bike lanes, paved shoulders and sidewalk from West Green Acres Street to West Jump Court.

View Factsheet
Contact Information
Construction Manager
Terry Muse
813-399-5383
Terry.Muse@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
kristen.carson@dot.state.fl.us
Lane Closures
  • Lane closed on northbound US 19 at the Grover Cleveland Boulevard / Halls River Road intersection

    Homosassa, FL -- Due to a depression in the roadway, the right lane of northbound US 19 is closed from north of Yulee Drive to the Grover Cleveland Boulevard / Halls River Road intersection. The lane will remain closed until further notice.

    Also, the westbound Grover Cleveland Boulevard right turn lane onto northbound US 19 is closed, along with one of the two left turn lanes from southbound US 19 onto eastbound Grover Cleveland Boulevard (the outside left turn lane is open).

Project Files
Project Images
Looking northwest over US 19 from the Green Acres Street area. (8/6/2021 photo)
Looking northwest on US 19 approaching Yulee Drive. (8/6/2021 photo)
Looking north over US 19 from Yulee Drive to the Halls River Rd. / Grover Cleveland Blvd. intersection. (8/6/2021 photo)
Looking north on US 19 from north of Homosassa Trail to the north end of the project. (8/6/2021 photo)
Looking east at a storm water drainage pond. (8/6/2021 photo)
Looking northwest over US 19 from the Green Acres Street area (7/8/2021 photo)
Looking northwest on US 19 approaching Yulee Dr. near the top of the photo (7/8/2021 photo)
Looking north over US 19 at the Halls River Rd. / Grover Cleveland Blvd. and Homosassa Trail intersections (7/8/2021 photo)
Looking north over US 19 at the split between two widening projects and storm water pond construction in the upper left of the photo (7/8/2021 photo)
Looking north at storm water pond construction on the west side of US 19 (7/8/2021 photo)
Looking northwest over US 19 from the Green Acres Street area (6/9/2021 photo)
Looking northwest on US 19 with traffic in final configuration approaching Yulee Dr. (curve area) (6/9/2021 photo)
Looking north over US 19 at the split between two widening projects and storm water pond construction in the upper left of the photo (6/9/2021 photo)
Storm water drainage pond construction near Jump Court (6/9/2021 photo)
Looking north at final stage construction from the south end of the project (south of Green Acres Street) to Bradshaw St. (3/8/2021 photo)
Looking north on US 19 with traffic in final configuration approaching Yulee Dr. (curve area) (3/8/2021 photo)
Looking north over US 19 from Homosassa Springs Visitor Center (bottom left) at final roadway alignment (3/8/2021 photo)
Looking north over US 19 from Halls River Road / Grover Cleveland Blvd. intersection (bottom) at final roadway alignment (3/8/2021 photo)
Looking north on US 19 at final paving from Elkhorn Drive (bottom) to Jump Court (top) (3/8/2021 photo)
Looking north at the transition between south and north US 19 projects at Jump Court (3/8/2021 photo)
Storm water drainage pond near Jump Court (March 8, 2021 photo)
Looking north at near final stage construction from the south end of the project (south of Green Acres Street) to Bradshaw St. (2/9/2021 photo)
Looking north on US 19 from Bradshaw Street to south of Yulee Dr. (2/9/2021 photo)
Looking north on US 19 with traffic in final configuration approaching Yulee Dr. (upper right corner) (2/9/2021 photo)
Looking north on US 19 with traffic in all new lanes from north of Yulee Dr. to Halls River Rd. / Grover Cleveland Blvd. (2/9/2021 photo)
Looking north over US 19 at traffic in final alignment from Halls River Rd. / Grover Cleveland Blvd. (bottom) to north of Homosassa Trail (2/9/2021 photo)
Looking north on US 19 at final paving from Faust Lane (bottom) to Jump Court (top) (2/9/2021 photo)
Looking north at the transition between south and north US 19 projects at Jump Court (2/9/2021 photo)
Drainage pond construction north of Jump Court (2/9/2021 photo)
Looking north over US 19 at the south end of the project. Widening is almost completed.(December 8, 2020 photo)
Looking northwest at US 19 (Yulee Drive is at the bend). Widening is nearing completion. (December 8, 2020 photo)
Looking north at US 19 widening work between Halls River Rd./Grover Cleveland Blvd. and Homosassa Trail (December 8, 2020 photo)
Looking north at US 19 construction where the two widening projects join. (December 8, 2020 photo)
Construction in the median of US 19 near Bradshaw Street (November 6, 2020 photo)
Finishing up the area of US 19 between Yulee Drive and Homosassa Trail (November 6, 2020 photo)
The US 19 corridor is taking shape, shown hear north of Homosassa Trail (November 6, 2020 photo)
Construction approaching the north end of the project (November 6, 2020 photo)
Construction near Jump Court (November 6, 2020 photo)
Storm drainage pond construction on the north end of the project (November 6, 2020 photo)
Median and drainage construction on US 19, just north of Green Acres Street (August 10, 2020 photo)
Looking northwest at US 19, with Yulee Drive near the top left of the photo. To the right, the northbound lanes are almost completed.  (August 10, 2020 photo)
Looking north on US 19 from the Yulee Drive intersection. (August 10, 2020 photo)
To the left in the photo, work continues to construct the southbound US 19 roadway just north of Homosassa Trail. (August 10, 2020 photo)
Work on the southbound US 19 roadway near Jump Court. Traffic is reduced to one lane in each direction on the northbound pavement. (August 10, 2020 photo)
Construction work on the west side of US 19 near Green Acres Street on August 4, 2020.
Construction work on the west side of US 19 near Green Acres Street on August 4, 2020.
Looking north at construction in median of the US 19 corridor near Green Acres Street. (July 7, 2020 photo)
Looking north at traffic shifted to the west side of the US 19 corridor south of Yulee Drive. (July 7, 2020 photo)
US 19 traffic is shifted to the east side of the corridor just north of Homosassa Trail. (July 7, 2020 photo)
Looking north at widening on the west side of the US 19 corridor at Faust Lane. (July 7, 2020 photo)
Looking north at widening on the north end of the project (July 7, 2020 photo)
Detour map for closure of Periwinkle Lane at the intersection on the east side of US 19
Looking north at US 19 widening at Jump Court (May 7, 2020 photo)
Looking north at US 19 widening near Jump Court (May 7, 2020 photo)
Looking north on US 19, just north of Homosassa Trail (May 7, 2020 photo)
Looking northwest at US 19 widening approaching Yulee Drive (May 7, 2020 photo)
Detour map for closure of Green Acres St. at US 19
Crews work next to the southbound lanes of US 19 near the south end of the project (2/19/20 photo)
Traffic is shifted to the west side of US 19 near the south end of the project (2/19/20 photo)
Both directions of traffic are shifted to the west side of the US 19 corridor near Yulee Drive (2/19/20 photo)
Looking south at the widened corridor at Homossassa Trail. The closed pavement will become the northbound lanes (2/19/20 photo)
New pavement for the northbound lanes of US 19 near the central part of the project (2/19/20 photo)
Crews work next to the southbound lanes of US 19 near the south end of the project (2/19/20 photo)
Crews work next to the southbound lanes of US 19 near the south end of the project (2/19/20 photo)
Crews work next to the southbound lanes of US 19 near the south end of the project (2/19/20 photo)
US 19 road widening just south of S. Jump Court (May 2019 photo).
Road base is being built on the east side of the US 19 corridor in the northern zone of the widening project (May 2019 photo).
Road widening work continues in the southern zone of the US 19 project in Homosassa (May 2019 photo).
Widening work is focused on the west side of the US 19 corridor in Homosassa Springs (June 2018 photo)
US 19 traffic has been shifted to the east side of the corridor near the US Post Office to focus on widening work on the west side (June 2018 photo)
US 19 near Homosassa Springs Wildlife State Park - November 2016
Temporary pavement construction near post office - March 2017
Early construction - November 2016
Looking southwest towards south end of project - February 2017
Early clearing near south end of project - February 2017
First month of construction - south end - November 2016
Drainage pond being built at north end of project - March 2017
Construction near Homosassa Trail - January 2017
Central project area - November 2016