Project Details
Phase Construction
County
Road
Construction Cost $7.8 million
Estimated Completion Late 2026
Contractor DB Civil Construction, Inc.
About

The improvements for this project consist of replacing a water main and force main at I-275/US 19 from north of the Skyway fishing pier to south of Pinellas Point Drive. 

Construction activities are expected to complete in late 2026. 

View Factsheet
Contact Information
Project Information
Maddie Griffin
727-575-8334
Maddie.Griffin@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.
Project Images
Crews prepare for reaming operations (February 2026 photo)
Dewatering pump operations (February 2026 photo)
Generator and fuel tanks power the dewatering pumps (February 2026 photo)
Crews prepare to install the watermain along I-275 (Sunshine Skyway Bridge) - December 2025 photo
Crews prepare to install the watermain along I-275 (Sunshine Skyway Bridge) - December 2025 photo
Looking south at west side of I-275 (Sunshine Skyway Bridge) - December 2025 photo