Project Details
Work Type Repaving
Phase Construction
Limits from Aberdeen Street to President Street
Project Start Late 2025
City
County
Road
Construction Cost $245,000
Estimated Completion Early 2026
Contractor Turtle Infrastructure Partners, LLC
About

This project involves milling and repaving approximately 300 feet of both the northbound and southbound travel lanes from north of Aberdeen Street to south of President Street in Pinellas County. 

In addition, the existing temporary concrete patch within the project limits will be removed and replaced as part of the roadway improvements.

Construction is anticipated to begin late 2025.

View Factsheet
Contact Information
Project Information
Bryce Johns
727-575-8334
Bryce.Johns@dot.state.fl.us
Media Contact
Kris Carson
813-976-6060
Kristen.Carson@dot.state.fl.us
Closures
  • Road Closure: Alt US 19 from Aberdeen Street to President Street

    Dunedin, FL – Beginning early morning Monday, December 1, the Florida Department of Transportation’s contractor will close all travel lanes on Alternate US 19 from Aberdeen Street to President Street for approximately one week, weather permitting.

    During this temporary road closure, motorists will have to detour around the work zone using Union Street, Patricia Avenue, Main Street/Skinner Boulevard, and Broadway. Access to businesses, residents, and emergency vehicles continues to be maintained.

    Advanced warning signs and message boards will assist drivers traveling through the area. Motorists should anticipate traffic delays and congestion on all nearby roads while traveling through the detour.  

    This road closure is part of the Alt US 19 repaving project from Aberdeen Street to President Street in Pinellas County. For more information on this project or to sign up for alerts, please visit FDOTTampaBay.com.