Project Details

Work Type Resurfacing
Phase Construction
Limits N Big Bass Trail to west of E Tasha Court
Project Start July 13, 2026
Length 1.87 miles
City
County
Road
Construction Cost $1.15 million
Estimated Completion fall 2026
Contractor C. W. Roberts Contracting, Incorporated

About

The purpose of this project is to preserve and extend the life of the existing pavement through resurfacing along this section of County Road 39 in Citrus County. 

Improvements will include milling and resurfacing, pavement markings, and signing.

Construction is underway as of July 13, 2026.

View Factsheet The link target will open in a new tab.

Contact Information

Project Information
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us

Closures

  • CR 39 (E Withlacoochee Trail) from N Big Bass Trail to west of E Tasha Court  
    Lane closures/ flagging operations: Monday, August 3 through Friday, August 7 from 7:30 a.m. to 5:30 p.m. 

Project Images

Milling old asphalt off CR 39 / E Withlacoochee Trail (7-21-2026 photo)
Placing new asphalt on CR 39 / E Withlacoochee Trail (7-21-2026 photo)
Rolling freshly placed asphalt on CR 39 / E Withlacoochee Trail (7-21-2026 photo)