Launch Recite Me assistive technology

EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Florida Department of
TRANSPORTATION

Project Details

Work Type
Resurfacing
Phase
Construction
Limits
N Big Bass Trail to west of E Tasha Court
Project Start
July 13, 2026
Length
1.87 miles
City
County
Road
Construction Cost
$1.15 million
Estimated Completion
fall 2026
Contractor
C. W. Roberts Contracting, Incorporated

About

The purpose of this project is to preserve and extend the life of the existing pavement through resurfacing along this section of County Road 39 in Citrus County. 

Improvements will include milling and resurfacing, pavement markings, and signing.

Construction is underway as of July 13, 2026.

View Factsheet The link target will open in a new tab.

Contact Information

Closures

  • There are no closures at this time.

Project Images