SR 694 (Park Boulevard) New Traffic Signal at 60th Street in Pinellas County
- Project ID
- 454839-1-54-01
Project Details
- Work Type
- New Traffic Signal
- Phase
- Construction
- Limits
- at 60th Street
- Project Start
- June 1, 2026
- City
- County
- Road
- Construction Cost
- $2.3 million
- Estimated Completion
- Summer 2027
- Contractor
- Cone & Graham, Inc.
About
This construction project is addressing safety improvements with the construction of a new traffic signal on SR 694 (Park Boulevard) at 60th Street in Pinellas County.
The mid-block pedestrian crossing just east of 60th Street will be removed.
Elements of work shall include, but are not limited to, installation of a new signalized intersection, roadway resurfacing, and sidewalk, pedestrian and lighting improvements.
Construction activities are underway and expected to be complete in summer 2027.
Contact Information
-
Project Information
- Name:
- Maddie Griffin
- Phone:
- 727-575-8334
- Email:
- Maddie.Griffin@dot.state.fl.us
-
Media Contact
- Name:
- Kris Carson
- Phone:
- 813-975-6060
- Email:
- Kristen.carson@dot.state.fl.us
Closures
-
SR 694 (Park Boulevard) at 60th Street
Lane closures: Monday, September 21 through Friday, September 25 from 8 a.m. to 5 p.m.