Project Details
Work Type Widening
Phase Construction
Limits from east of Curley Road to east of Morris Bridge Road
Project Start November 2017
Length 4.5 miles
City
County
Road
Construction Cost $42.5 million
Estimated Completion Late 2021
Contractor D.A.B. Constructor, Inc.
About

Traffic Advisory: Eastbound traffic was shifted on November 8, 2020 to a two-direction alignment on the new portion of SR 54 from west of Wesley Chapel Loop to New River Road. This temporary, new alignment restored left turns in this stretch of the roadway.

_______________________________________________

This project will widen the existing two-lane road to a four-lane road with medians.

A sidewalk will be built on the north side of the road and a 10-foot wide multi-use trail will be built on the south side. 

This $42.5 million project is expected to finish in late 2021. 

 

 

View Factsheet
Contact Information
Construction Manager
Zach Stringer
352-848-2600
Zachary.Stringer@dot.state.fl.us
Media Contact
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Project Files
Project Images
Old pavement has been removed to begin construction of new eastbound lanes, east of Curley Road (December 13, 2020 photo)
Construction at the intersection of SR 54 and Meadow Pointe Blvd. (December 13, 2020 photo)
All traffic is on new westbound pavement west of New River Road for construction of new eastbound lanes (December 13, 2020 photo)
Traffic has been shifted to new pavement approaching Morris Bridge Road to begin construction of new westbound lanes (December 13, 2020 photo)
Looking east at SR 54 between Smith Road and Meadow Pointe Boulevard. (July 15, 2020 photo)
Looking east at SR 54, approaching River Glen Boulevard. (July 15, 2020 photo)
Looking east at SR 54 widening. Lado Drive is near the top of the photo. (July 15, 2020 photo)
Looking east on SR 54 at the Hanbury Drive / New River Road intersection. (July 15, 2020 photo)
Looking east at SR 54 construction at Fox Wood Blvd. (May 19, 2020 photo)
Looking east at SR 54 widening work (May 19, 2020 photo)
SR 54 Widening Project - May 2020
SR 54 Widening Project - May 2020
SR 54 Widening Project - May 2020
SR 54 Widening Project - May 2020
SR 54 Widening Project - April 2020
SR 54 Widening Project - April 2020
SR 54 Widening Project - April 2020
SR 54 Widening Project - April 2020
SR 54 Widening Project - April 2020
SR 54 Widening Project - April 2020
SR 54 Widening Project - April 2020
SR 54 Widening Project - April 2020
SR 54 Widening Project - March 2020
SR 54 Widening Project - March 2020
SR 54 Widening Project - March 2020
SR 54 Widening Project - March 2020
SR 54 Widening Project - February 2020
SR 54 Widening Project - February 2020
SR 54 Widening Project - February 2020
SR 54 Widening Project - February 2020
SR 54 Widening Project - February 2020
SR 54 Widening Project - January 2020
SR 54 Widening Project - January 2020
SR 54 Widening Project - January 2020
SR 54 Widening Project - January 2020
SR 54 Widening Project - January 2020
SR 54 Widening Project - January 2020
SR 54 Widening Project - January 2020
SR 54 Widening Project - January 2020
SR 54 Widening Project - December 2019
SR 54 Widening Project - December 2019
SR 54 Widening Project - December 2019
SR 54 Widening Project - December 2019
SR 54 Widening Project - November 2019
SR 54 Widening Project - November 2019
SR 54 Widening Project - November 2019
SR 54 Widening Project - November 2019
SR 54 Widening Project - September 2019
SR 54 Widening Project - September 2019
SR 54 Widening Project August 2019
SR 54 Widening Project August 2019
SR 54 Widening April 2018
SR 54 Widening II April 2018