Project Details
Work Type Widening
Phase Construction
Limits From Jump Court to Fort Island Trail
Project Start November 2018
Length 4.7 miles
City
County
Road
Construction Cost $51.1 million
Estimated Completion Fall 2022
Contractor D.A.B. Constructors, Inc.
About

This project includes widening US 19 from Jump Court to Fort Island Trail from four lanes to six lanes in Citrus County.

A shared use path, sidewalks and storm water ponds will also be added as part of the project.

Construction is expected to finish in the fall of 2022.

View Factsheet
Contact Information
Construction Manager
Austin Petersen
352-848-2653
Austin.Petersen@dot.state.fl.us
Media Contact
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Lane Closures
  • US 19 from Jump Court to Fort Island Trail
    Day lane closures: Sunday, April 18 through Saturday, April 24 from 7 a.m. to 5:30 p.m. 
    Night lane closures: Sunday, April 18 through Friday, April 23 from 8 p.m. to 6 a.m.

Project Files
Project Images
Looking northwest over US 19 north of Jump Ct. (bottom) at the south end of the project (3/8/2021 photo)
Looking north over construction in the media of US 19 north of Goodman Lane towards Dixieland St. (3/8/2021 photo)
Looking north over US 19 towards Venable St. at construction of the new northbound alignment (3/8/2021 photo)
Looking northeast over US 19 construction towards Mayo Drive (3/8/2021 photo)
Looking north over US 19 from W. White Dogwood Drive to W. Longfellow Street (2/9/2021 photo)
Looking north over US 19 from north of Dixieland Street to Kimberly Ct. (2/9/2021 photo)
Looking north over US 19 from Highlands St. to north of Ozello Trail (2/9/2021 photo)
Looking north over US 19 from Venable St. to south of Godfrey St. (2/9/2021 photo)
Widening of US 19 near Goodman Lane (November 6, 2020 photo)
Widening on the east side of US 19 between Dixieland Street and Highland Street (November 6, 2020 photo)
Widening on the east side of US 19 between Highland Street and Ozello Trail (November 6, 2020 photo)
Widening on the east side of US 19 at Ozello Trail (November 6, 2020 photo)
Looking north at US 19 near Sugar Bush Path (July 7, 2020 photo)
Looking north at US 19 widening construction near Goodman Lane (July 7, 2020 photo)
Looking north at US 19 widening construction near Goodman Lane (July 7, 2020 photo)
Looking north at US 19 construction, just north of White Dogwood Drive. A portion of the new northbound lanes has been paved. (July 7, 2020 photo)
Looking north at US 19 widening construction near Goodman Lane (May 7, 2020 photo)
Looking north at US 19 construction, just north of White Dogwood Drive (May 7, 2020 photo)
US 19 Widening from Jump Ct to Fort Island Trail Project - May 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - May 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - May 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - May 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - April 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - April 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - April 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - April 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - Clearing Activities April 2020
US 19 Widening from Jump Ct to Fort Island Trai Project - Drainage Installation April 2020
US 19 Widening from Jump Ct to Fort Island Trail Project - Drainage Installation - April 2020
US 19 Widening from Jump Ct to Fort Island Trail - Traffic Shift Northend of Project - April 2020
US 19 Widening from Jump Ct to Fort Island Trail - Traffic Shift Southend of Project - April 2020
US 19 Widening from Jump Ct to Fort Island Trail - March 2020
US 19 Widening from Jump Ct to Fort Island Trail - March 2020
US 19 Widening from Jump Ct to Fort Island Trail - March 2020
US 19 Widening from Jump Ct to Fort Island Trail - March 2020
US 19 Widening from Jump Ct to Fort Island Trail - March 2020
US 19 Widening from Jump Ct to Fort Island Trail - March 2020
US 19 Widening from Jump Ct to Fort Island Trail - March 2020
US 19 Widening from Jump Ct to Fort Island Trail - March 2020
US 19 Widening from Jump Ct to Fort Island Trail - February 2020
US 19 Widening from Jump Ct to Fort Island Trail - February 2020
US 19 Widening from Jump Ct to Fort Island Trail - February 2020
US 19 Widening from Jump Ct to Fort Island Trail - February 2020
US 19 Widening from Jump Ct to Fort Island Trail - February 2020
US 19 Widening from Jump Ct to Fort Island Trail - February 2020
US 19 Widening from Jump Ct to Fort Island Trail - February 2020
US 19 Widening from Jump Ct to Fort Island Trail - January 2020
US 19 Widening from Jump Ct to Fort Island Trail - January 2020
US 19 Widening from Jump Ct to Fort Island Trail - January 2020
US 19 Widening from Jump Ct to Fort Island Trail - January 2020
US 19 Widening from Jump Ct to Fort Island Trail - December 2019
US 19 Widening from Jump Ct to Fort Island Trail - December 2019
US 19 Widening from Jump Ct to Fort Island Trail - December 2019
US 19 Widening from Jump Ct to Fort Island Trail - December 2019
US 19 Widening from Jump Ct to Fort Island Trail - November 2019
US 19 Widening from Jump Ct to Fort Island Trail - November 2019
US 19 Widening from Jump Ct to Fort Island Trail - November 2019
US 19 Widening from Jump Ct to Fort Island Trail - November 2019
US 19 Widening from Jump Ct to Fort Island Trail - October 2019
US 19 Widening from Jump Ct to Fort Island Trail - October 2019
US 19 Widening from Jump Ct to Fort Island Trail - October 2019
US 19 Widening from Jump Ct to Fort Island Trail - October 2019
US 19 Widening from Jump Ct to Fort Island Trail - October 2019
US 19 Widening from Jump Ct to Fort Island Trail - October 2019