Project Details
Work Type Median Safety and urban corridor Improvements
Phase Construction
Limits From Memorial Highway/Sheldon Road to Himes Avenue
Project Start August 2020
City
County
Road
Construction Cost $3,572,268.91
Estimated Completion Fall 2021
Contractor C.W. Roberts Contracting, Inc.
About

The project will change, relocate or close medians on SR 580 (Hillsborough Avenue) between Memorial Highway/Sheldon Road and Himes Avenue in Hillsborough County to increase corridor safety.

It will also provide multi-modal improvements at multiple locations along the corridor including pedestrian signal modifications, crosswalk improvements and minor drainage improvements at the intersections of Town N Country Boulevard, Hanley Road and Anderson Road. The project will also provide an alternative bike route in the eastbound direction from Dale Mabry Highway to Himes Avenue.

Construction activities are anticipated to finish in the fall of 2021.

This project has been combined with 437641-2 into a single construction project.  All updates will be made to this page.

View Factsheet
Contact Information
Construction Manager
Shiva Moonian
813-612-3200
Shiva.Moonian@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • SR 580 (Hillsborough Avenue) from Memorial Highway/Sheldon Road to Himes Avenue
    Lane closures: Monday, November 2 through Friday, November 6 from 10 p.m. to 6:30 a.m.