Project Details
Work Type Repaving
Phase Construction
Limits from north of 44th Ave to north of Park Blvd
Project Start Summer 2021
Length 2 miles
City
County
Road
Construction Cost $4,460,659.51
Estimated Completion Spring 2022
Contractor Preferred Materials Inc.
About

This project will repave US 19 between 44th Ave and Park Blvd in Pinellas County. 

Construction is anticipated to begin in the summer of 2021 and be complete in the spring of 2022.