Project Details
Work Type Widening
Phase Completed
Limits from SR 44 to south of the Withlacoochee State Trail
Length 1 mile
City
County
Road
About

As of August 13, 2025, all construction activities associated with this project have been completed.  

This project widened US 41 from SR 44 (W Main Street) to south of the bridge over the Withlacoochee State Trail from a two-lane roadway to a four-lane divided road with bike lanes and sidewalks. New traffic signals were installed at a realigned intersection of US 41 / Montgomery Avenue /Zephyr Street and at the US 41 intersection at the Inverness Regional shopping center. Signal upgrades were made at the US 41 / SR 44 intersection.

The improvements on this project included:

  • Added one lane in each direction.
  • Added a median separation.
  • Added street lighting to all signalized intersections.
  • Provided bicycle lanes adjacent to travel lane in each direction.
  • Provided sidewalks on both sides.
  • Pedestrian safety upgrades at intersections.
  • Added a dedicated left turn lane for the southbound traffic going to Inverness Middle School.
  • Provided a shared used path to connect sidewalks to the Withlacoochee State Trail (WST) at the north end of the project. The WST was not impacted by this project.

_____________________________________________

PROGRESS REPORT

June 27, 2025 - All barrels have been removed from US 41 and all lanes are now open to traffic from SR 44 to south of the bridge over the Withlacoochee State Trail as of June 27, 2025. Previously, just one lane was open in each direction to allow traffic separators to be built and median construction to be completed.

_____________________________________________
New alignment of Montgomery Avenue at US 41 intersection

As of January 23, 2024, Montgomery Avenue now intersects with US 41 across from Zephyr Street. Traffic signals control movements at the intersection for US 41, Montgomery Avenue, and Zephyr Street
._____________________________________________
TRAFFIC NEWS >>> PERMANENT ROAD CLOSURES

  • The Talmage Avenue connection at the westbound SR 44 ramp to northbound US 41 was closed permanently on Monday, October 30, 2023.
  • Tompkins Street from US 41 to Ella Avenue was closed permanently on Wednesday, January 3, 2024.


Click to view the Virtual Open house Tour

View Factsheet
Contact Information
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Closures
  • There are no closures at this time.
Project Files
Project Videos
Project Images
Looking northwest over SR 44 and US 41 to north of the Montgomery Avenue / Zephyr Street intersection (7-24-2025 photo)
Looking north over US 41 from the Montgomery Ave. / Zephyr St. intersection to Middle School Road (7-24-2025 photo)
Looking north over US 41 from south of Middle School road to the north end of the project (7-24-2025 photo)
Looking northwest over SR 44 and US 41 to north of the Montgomery Avenue / Zephyr Street intersection (6-18-2025 photo)
Looking north over US 41 from the Montgomery Ave. / Zephyr St. intersection to Middle School Road (6-18-2025 photo)
Looking north over US 41 from south of Middle School road to north of the north end of the project (6-18-2025 photo)
Getting closer to opening the second lane on northbound US 41, just north of SR 44 (5-19-2025 photo)
Southbound US 41 as school lets out (5-19-2025 photo)
Looking southwest on US 41 at final preparations to open all lanes (5-19-2025 photo)
Traffic signal work at the Inverness Regional shopping center driveway (5-19-2025 photo)
Traffic signal work at the Inverness Regional shopping center driveway (5-19-2025 photo)
Traffic signal work at the Inverness Regional shopping center driveway (5-19-2025 photo)
Looking northwest over SR 44 and US 41 to north of the Montgomery Avenue / Zephyr Street intersection (3-18-2025 photo)
Looking north over US 41 from the Montgomery Ave. / Zephyr St. intersection to Middle School Road (3-18-2025 photo)
Looking north over US 41 from south of Middle School road to the north end of the project (3-18-2025 photo)
Looking northwest over SR 44 and US 41 to north of the Montgomery Avenue / Zephyr Street intersection (1-17-2025 photo)
Looking north over US 41 from the Montgomery Ave. / Zephyr St. intersection to south of Middle School Road (1-17-2025 photo)
Looking north over US 41 at the north end of the project (1-17-2025 photo)
Looking northwest on US 41, north of SR 44 (12-20-2024 photo)
Looking northwest on US 41 towards the Montgomery Avenue / Zephyr Street intersection (12-20-2024 photo)
Looking south on US 41, just south of the Withlacoochee State Trail (12-20-2024 photo)
Looking south on US 41 approaching Middle School Drive (12-20-2024 photo)
Looking south on US 41 at Middle School Drive (12-20-2024 photo)
Looking south on US 41 at the Inverness Regional shopping center intersection (12-20-2024 photo)
Looking southwest on US 41 approaching the Montgomery Avenue/Zephyr Street intersection (12-20-2024 photo)
Looking southeast on US 41 at the Montgomery Avenue/Zephyr Street intersection (12-20-2024 photo)
Looking southeast on US 41 towards SR 44 (12-20-2024 photo)
Looking north on US 41 towards the bridge over the Withlacoochee State Trail (12-20-2024 photo)
Looking northwest over SR 44 and US 41 to north of the Montgomery Avenue / Zephyr Street intersection (11-19-2024 photo)
Looking north over US 41 from the Montgomery Ave. / Zephyr St. intersection to north of Middle School Road (11-19-2024 photo)
Looking north over US 41 from south of Middle School Rd. to north of the Withlacoochee State Trail (11-19-2024 photo)
Looking northwest over SR 44 and US 41 to north of the Montgomery Avenue / Zephyr Street intersection (9-18-2024 photo)
Looking north over US 41 from the Montgomery Ave. / Zephyr St. intersection to north of Middle School Road (9-18-2024 photo)
Looking north over US 41 from south of Middle School Rd. to north of the Withlacoochee State Trail (9-18-2024 photo)
Traffic shifted to the east side of the US 41 corridor (8/23/2023 photo)
Traffic approaches after crossing the Withlacoochee State Trail and is shifted to the east side of the US 41 corridor (8/23/2023 photo)
Traffic shifted to the east side of the US 41 corridor (8/23/2023 photo)
Traffic shifted to the east side of the US 41 corridor (8/23/2023 photo)
Traffic shifted to the east side of the US 41 corridor (8/23/2023 photo)
Looking northwest over SR 44 and US 41 to north of the Montgomery Avenue / Zephyr Street intersection (7-18-2024 photo)
Looking northwest over US 41 at the Montgomery Avenue / Zephyr Street intersection (7-18-2024 photo)
Looking north over US 41 from the Inverness Regional Shopping Center to Middle School Road (7-18-2024 photo)
Looking north over US 41 from south of Middle School Road to north of the bridge over the Withlacoochee State Trail (7-18-2024 photo)
Zephyr Street has been reopened at US 41. (8/14/2024 photo)
Zephyr Street has been reopened at US 41. (8/14/2024 photo)
Looking northwest over US 41 from SR 44 to north of Montgomery Avenue (5-20-2024 photo)
Looking north at US 41 from Montgomery Ave. / Zephyr Street (5-20-2024 photo)
Looking north at roadway widening at the north end of the project (5-20-2024 photo)
Looking northwest over US 41 from SR 44 to north of Montgomery Avenue (3-21-2024 photo)
Looking north at roadway widening on the west side of US 41 from Montgomery Ave. / Zephyr Street (3-21-2024 photo)
Looking north at shared use path construction and roadway widening at the north end of the project (3-21-2024 photo)
Drainage and shared use path construction on the west side of the US 41 corridor (2-16-2024 photo)
Shared use path construction on the west side of the US 41 corridor (2-16-2024 photo)
Looking south at construction on the west side of US 41 approaching Montgomery Avenue (2-16-2024 photo)
Work on the west side of US 41 just north of Montgomery Avenue (2-16-2024 photo)
Work on the west side of the US 41 corridor (2-16-2024 photo)
Storm water drainage pond construction (2-16-2024 photo)
Looking northwest over US 41 from SR 44 to north of Montgomery Avenue (1-22-2024 photo)
Looking north at the realigned Montgomery Ave. intersection at US 41 and Zephyr Street (1-22-2024 photo)
Looking north over US 41 at the project's north end, south of the bridge over the Withlacoochee State Trail (1-22-2024 photo)
Looking southeast on US 41 from the realigned Montgomery Avenue intersection (1-23-2024 photo)
Looking east from Montgomery Avenue at the realigned intersection with US 41 and Zephyr Street (1-23-2024 photo)
Groundbreaking ceremony site on east side of US 41 (11-30-2023 photo)
Citrus High School ROTC’s Color Guard presents the flags during the groundbreaking ceremony (11-30-2023 photo)
FDOT District Seven Secretary David W. Gwynn, P.E. emcees the groundbreaking ceremony (11-30-2023 photo)
Holly L. Davis, Citrus County Commission Chair speaks during the groundbreaking event (11-30-2023 photo)
US 41 traffic and construction is in the background of the groundbreaking event (11-30-2023 photo)
Inverness City Manager, Eric Williams, shares project history during the groundbreaking ceremony (11-30-2023 photo)
Inverness Mayor Bob Plaisted addresses the attendees at the groundbreaking ceremony (11-30-2023 photo)
After the official "shovels in the ground" ceremony, FDOT and contractor staff turn a little dirt (11-30-2023 photo)
Looking northwest over US 41 from SR 44 to north of Montgomery Avenue (11-20-2023 photo)
Looking north from the Montgomery Avenue intersection with US 41 (11-20-2023 photo)
Looking north over US 41 at the project's north side which ends south of the bridge over the Withlacoochee State Trail (11-20-2023 photo)
Construction underway on the east side of US 41, south of Zephyr Street (11.15.2023 photo)