US 41 Widening From S of Withlacoochee Trail Bridge to N of Sportsman Point 257165-4-52-01
Project Details
| Work Type | Widening |
|---|---|
| Phase | Design |
| Limits | From S of Withlacoochee Trail Bridge to N of Sportsman Point |
| Length | 1.2 miles |
| City | |
| County | |
| Road | |
| ROW Cost | $9.1M |
About
The purpose of this project is to reconstruct and widen US 41 from the existing 2 lanes to a 4-lane road with median separation. The project also includes bike lanes, sidewalks, new bridges over the Withlacoochee Trail, a mid-block pedestrian crossing, and new pond sites.
The project is currently in the design phase. Construction activities are anticipated to begin during late 2027.