Project Details
Work Type Median Modifications
Phase Construction
Limits from 30th Ave N. to 94th Ave N.
Project Start Early 2023
Length 4 miles
City
County
Road
Construction Cost $7.1M
Estimated Completion Summer 2024
About

This project includes extending left turn lane storage at nine signalized intersections and 15 left turn lanes at existing median openings along the corridor. Some existing median openings will be modified, and others will be closed. Additionally, nine mid-block pedestrian crossings will be built. 

Construction is anticipated to begin early 2023.