Project Details
Work Type Sidewalk
Phase Construction
Limits from Oscar Hill Rd to Dixie Hwy
Project Start August 2020
Length .3 miles
City
County
Road
Construction Cost $1,622,282
Estimated Completion Spring 2021
Contractor David Nelson Construction Co.
About

This project will add sidewalks along both sides of Alt. US 19 (Pinellas Avenue) between Oscar Hill Road and Dixie Highway in Tarpon Springs.

In addition, a new mid-block pedestrian crossing with a rectangular rapid flashing beacon will be installed between Anclote Road and Fulton Street.  

The $1.6 project is expected to finish in the spring of 2021.