US 41 Repaving from County Line Rd to Bell Lake Rd & SR 54 Repaving from US 41 to east of Knight Rd 441659-1-52-01 & 441658-1-52-01
Project Details
Work Type | Repaving |
---|---|
Phase | Construction |
Project Start | November 13, 2023 |
City | |
County | |
Road | |
Construction Cost | $13 million |
Estimated Completion | Fall 2024 |
Contractor | Ajax Paving Industries of Florida LLC |
About
Two projects have been combined to be built under one construction contract:
- Repaving 3.25 miles on US 41 between County Line Road and Bell Lake Road (project 441659-1-52-01).
- Repaving 0.75 miles on SR 54 between US 41 and Knight Road (project 441658-1-52-01).
The improvements in this project include milling and resurfacing, pavement reconstruction, pavement markings, drainage improvements, pedestrian / bicyclist enhancements, signage, and sidewalk repairs.
Construction began November 13, 2023.
View Factsheet
Contact Information
Project Information |
---|
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
|
Closures
-
US 41 (Land O’ Lakes Boulevard) at SR 54 to Bell Lake Road
Lane closures (northbound): Monday, April 22 through Friday, April 26 from 8:30 a.m. to 3:30 p.m.