SR 44 (Gulf to Lake Hwy) Repaving from Norvell Bryant Hwy to west of N Lopp Point 432582-1-52-01
Project Details
Work Type | Repaving |
---|---|
Phase | Construction |
Limits | from Norvell Bryant Hwy to west of N. Lopp Point |
Project Start | October 14, 2023 |
Length | 2.4 miles |
City | |
County | |
Road | |
Construction Cost | $5.9 million |
Estimated Completion | Spring 2024 |
Contractor | Superior Asphalt, Inc. |
About
This project will mill and resurface SR 44 (Gulf to Lake Highway) between Norvell Bryant Highway and North Lopp Point.
Other work will include safety improvements such as sidewalk connectivity, sidewalk repairs, curb ramp reconstruction, and pedestrian lighting installed at signalized intersections. Signing, pavement markings, and minor drainage improvements will also take place throughout the project area and there will be signalization upgrades at N Rock Crusher Road.
Construction is underway as of October 14, 2023.
Contact Information
Project Information |
---|
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
|
Closures
-
SR 44 from Norvell Bryant Highway to Lopp Point
Lane closures (eastbound): Sunday, December 3 through Friday, December 8 nights from 8 p.m. to 6 a.m.