Project Details
Work Type Repaving
Phase Construction
Limits from Norvell Bryant Hwy to west of N. Lopp Point
Project Start October 14, 2023
Length 2.4 miles
City
County
Road
Construction Cost $5.9 million
Estimated Completion Spring 2024
Contractor Superior Asphalt, Inc.
About

This project will mill and resurface SR 44 (Gulf to Lake Highway) between Norvell Bryant Highway and North Lopp Point.

Other work will include safety improvements such as sidewalk connectivity, sidewalk repairs, curb ramp reconstruction, and pedestrian lighting installed at signalized intersections. Signing, pavement markings, and minor drainage improvements will also take place throughout the project area and there will be signalization upgrades at N Rock Crusher Road.

Construction is underway as of October 14, 2023. 

 

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Closures
  • SR 44 from Norvell Bryant Highway to Lopp Point
    Lane closures (eastbound): Sunday, December 3 through Friday, December 8 nights from 8 p.m. to 6 a.m.