Project Details
Work Type Repaving
Phase Design
Limits Leonard Dr to Delaware St
Length 1.5 miles
City
Road
Design Cost $900,000
About

This project consists of repaving SR 590 in Safety Harbor between Leonard Dr. and Delaware Street.  Curb ramps will be modified to meet current ADA Standards.  The sidewalks will also be studied to determine if they can be widened.

Design is underway.

Construction is anticipated to begin summer 2023.