SR 60 (Kennedy Boulevard) Repaving from Woodlynne Avenue to Brevard Avenue
- Project ID
- 436489-1-52-01
Project Details
- Work Type
- Repaving
- Phase
- Construction
- Limits
- from Woodlynne Avenue to Brevard Avenue
- Project Start
- August 23, 2025
- Length
- 1.8 miles
- City
- County
- Road
- Construction Cost
- $23 million
- Estimated Completion
- Late 2027
- Contractor
- Watson Civil Construction, Inc.
About
Construction activities are ongoing as part of the State Road 60 (Kennedy Boulevard) repaving and drainage improvement project from Woodlynne Avenue to Brevard Avenue in Tampa.
Improvements include resurfacing the roadway, replacing the drainage system, updating curb ramps and sidewalks to ADA standards, and installing new traffic signals at Habana Avenue, Fremont Avenue, and Oregon Avenue.
Work is taking place during daytime and nighttime hours. Temporary lane closures on Kennedy Boulevard may occur at night from 10 p.m. to 6:30 a.m., along with side street closures for drainage installation work.
To construct the project, heavy machinery is being used during daytime and nighttime hours and may at times produce construction noise and vibrations, and require the use of bright lights.
Access to driveways, sidewalks, and side streets (via temporary detour route) continues to be maintained.
Motorists are reminded to use caution when traveling through the work zone and remain alert for pedestrians, cyclists, and construction workers.
This project is expected to finish in late 2027.
Contact Information
-
Project Information
- Name:
- Maricelle Venegas
- Phone:
- 813-975-6204
- Email:
- Maricelle.Venegas@dot.state.fl.us
-
Media Contact
- Name:
- Kayla Mejia
- Phone:
- 813-975-6060
- Email:
- Kayla.Mejia@dot.state.fl.us
Closures
-
SR 60 (Kennedy Boulevard) from Woodlynne Avenue to Brevard Avenue
Lane closures: Sunday, November 8 through Thursday, November 12, nights from 10 p.m. to 6:30 a.m. -
Oregon Avenue closing just south of Kennedy Boulevard for drainage installation work
A temporary road closure begins 10 p.m., Thursday, November 5 and continues through 6:30 a.m., Friday, November 20
DETOUR: Motorists traveling on Kennedy Blvd needing to access Oregon Avenue will have to use either Dakota Avenue or Willow Avenue and Cleveland Street during this temporary road closure.
For more information on this closure, please email roadwork@dot.state.fl.us or call 813-975-6204.