Project Details
Work Type Repaving
Phase Construction
Limits from S Woodlynne Avenue to N Brevard Avenue
Project Start Fall 2025
Length 1.8 miles
City
County
Road
Construction Cost $23 million
Estimated Completion Fall 2027
Contractor Watson Civil Construction, Inc.
About

The State Road 60 (Kennedy Boulevard) roadway improvements will preserve and extend the life of the existing pavement by milling and resurfacing pavement in this area of Tampa.

Curb ramps will be upgraded to comply with current ADA standards and general safety modification work will be completed including wider sidewalk throughout the project limits.

New traffic signals will be installed at the intersections of Habana Avenue, Fremont Avenue, and Oregon Avenue.

Bus stop, special emphasis cross walks, and other traffic operational improvements will be incorporated.

This project will also replace and rehabilitate the existing drainage system.

Construction activities are expected to begin fall of 2025.

View Factsheet
Contact Information
Project Information
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.