SR60 (Kennedy Blvd) Repaving from Woodlynne Ave to Brevard Ave 436489-1-52-01
Project Details
Work Type | Repaving |
---|---|
Phase | Design |
Limits | from west of Woodlynne Ave to East of Brevard Ave |
Length | 1.8 miles |
City | |
County | |
Road | |
Design Cost | $2.37 million |
About
This project will repave Kennedy Boulevard (SR 60) from Woodlynne Avenue to Brevard Avenue west of Downtown Tampa.
Traffic signals will be installed at Habana Avenue, Fremont Avenue and Oregon Avenue. Drainage upgrades are also included along the corridor.
The project is currently being designed. Construction is anticipated to begin fall 2024.
View Factsheet
Contact Information
Design Manager |
---|
Kevin Lee
813-975-6426
Kevin.Lee@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.