SR 60 (Kennedy Boulevard) Repaving from Woodlynne Avenue to Brevard Avenue 436489-1-52-01
Project Details
Work Type | Repaving |
---|---|
Phase | Construction |
Limits | from S Woodlynne Avenue to N Brevard Avenue |
Project Start | August 23, 2025 |
Length | 1.8 miles |
City | |
County | |
Road | |
Construction Cost | $23 million |
Estimated Completion | Spring 2027 |
Contractor | Watson Civil Construction, Inc. |
About
>>>New Traffic Pattern Coming to Kennedy Boulevard between Armenia Avenue and Willow Avenue<<<
Construction activities have begun as part of the State Road 60 (Kennedy Boulevard) repaving project from Woodlynne Avenue to Brevard Avenue in Tampa.
Additional improvements include replacing the drainage system, updating curb ramps and sidewalks to ADA standards, and installing new traffic signals at Habana Avenue, Fremont Avenue, and Oregon Avenue.
Work is taking place during the day and at night. At times, travel lanes may close from 10 p.m. to 6:30 a.m.
Access to driveways, sidewalks, and side streets will be maintained during this project.
Motorists are reminded to use caution when traveling through the work zone and remain alert for pedestrians and construction workers.
This project is expected to finish in the spring of 2027.
Contact Information
Project Information |
---|
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
-
SR 60 (Kennedy Boulevard) from Armenia Avenue to Rome Avenue
Lane closures: Sunday, October 12 through Thursday, October 16 nights from 10 p.m. to 6:30 a.m.