Project Details
Work Type ITS
Phase Construction
Project Start Summer 2021
City
County
Road
Construction Cost $1,887,858.10
Estimated Completion Spring 2022
Contractor Highway Safety Devices, Inc.
About

This project will install wrong way detection devices on interstate ramps in Hillsborough County and Pinellas County.

Devices will be installed at the following locations;

  • I-4 Eastbound at Exit 3 (Columbus Dr. and US 41/ 50th St.) 
  • I-75 southbound at Exit 265 (Fowler Ave)
  • I-75 northbound at Exit 265 (Fowler Ave)
  • I-175  at Dr. MLK Jr. Blvd S and 6th St. S.
  • I-275 at Exit 16 (Sunshine Skyway Lane S.,
  • I-275 at Exit 17 (Pinellas Bayway and 54th Ave. S)
  • I-275 at Exit 18 (26th Ave. S)
  • I-275 at Exit 21 (28th Ave. S) 
  • I-275 at Exit 23B (5th Ave. N)
  • I-275 southbound at Exit 41A (US 92/Dale Mabry Hwy)
  • I-275 northbound at Exit 44 (Ashley Dr. and Scott St)
  • I-275 northbound at Exit 49 (Bird St) 
  • I-275 southbound at Exit 50 (Busch Blvd)
  • I-375 at 8th St. N.

Construction is anticipated to begin in the summer of 2021 and be complete in the Spring of 2022.

View Factsheet
Contact Information
Construction Manager
Sarah Gansz
727-575-8300
sarah.gansz@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.