Project Details
Work Type Safety Improvements
Phase Construction
Limits Intersection
Project Start September 20, 2021
City
County
Road
Construction Cost $278,094.79
Estimated Completion Late 2021
Contractor Cone & Graham, Inc.
About

This design-build project is making safety improvements by adding a new traffic signal at SR 200 (Carl G Rose Highway) and CR 491 (Lecanto Highway) in Citrus County.  

Improvements include the installation of a new traffic signal, roadway lighting, signage and pavement markings, and the addition of pedestrian signals and crosswalks. 

Status: Construction is estimated to finish by late 2021  

 

 

View Factsheet
Contact Information
Construction Manager
Randy Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • SR 200 (Carl G Rose Highway) at CR 491 (Lecanto Highway)
    Lane closures: Monday, September 20 through Friday, September 24 from 6 a.m. to 6 p.m. (westbound only)