Project Details
Work Type Pedestrian Safety Improvement
Phase Construction
Limits Intersection
Project Start Design Underway/Construction Starts Fall of 2021
City
County
Road
Construction Cost $163,613.05
Estimated Completion Early 2022
Contractor Cone & Graham, Inc
About

This design-build project is making pedestrian safety improvements by constructing curb ramps and adding crosswalks to the intersection of US 19 and Main Street in Pasco County. 

Improvements include: 

  • construction of traffic separator, sidewalk, and curb ramps
  • installation of signage and pavement markings 
  • addition of pedestrian signals and crosswalks

Status: Design Phase ongoing, construction is anticipated to begin fall of 2021

View Factsheet
Contact Information
Construction Manager
Randy Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.