Work Type Safety Improvements
Phase Construction
Limits US 19 at SR 54
Project Start July 2021
City
County
Road
Construction Cost $471,453.92
Estimated Completion Late 2021
Contractor Cone & Graham, Inc
About

This design-build project is extending the southbound dual left turn lanes to the north of the existing signalized intersection at US 19 and SR 54 in Pasco County.  

Improvements include: 

  • roadway widening
  • milling and resurfacing
  • signing and pavement markings 

Construction is anticipated to begin July and finish by late 2021.  

View Factsheet
Contact Information
Construction Manager
Randy Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.