US 19 Interchange Improvement at Gandy Blvd 435914-3-52-01
Project Details
Work Type | Interchange Improvement |
---|---|
Phase | Completed |
Limits | from south of Gandy Blvd to north of 78th Ave. |
City | |
County | |
Road |
About
As of September 7, 2023, all construction activities associated with this project have been completed.
This project will add additional left turn lane from southbound US 19 onto the eastbound Gandy Blvd entrance ramp. 78th Avenue will also be repaved between US 19 and 43rd Street.
Construction is underway and anticipated to be complete in the fall of 2023.
View Factsheet
Contact Information
Media Contact |
---|
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.