Project Details
Work Type Roundabout
Phase Construction
Length 8 miles
City
County
Road
Construction Cost $10.2 million
Estimated Completion Summer 2025
Contractor Watson Civil Construction, Inc.
About

Two projects have been combined to be built under one design-build construction project:

  1. Resurfacing of CR 52 from west of Storch Lane to US 98/US 301 (439832-1-52-01); and 
  2. CR 52 at College Avenue / Pompanic Street Roundabout (439832-3-52-01).

The project will repave CR 52 (formerly SR 52) from west of Storch Lane in San Antonio to east of Smith Road in Dade City, and from south of Center Avenue to US 98/US 301 in Dade City. Resurfacing from east of Smith Road to south of Center Avenue was done under a previous project (429076-4).

A roundabout has been constructed at the intersection of CR 52 and College Avenue / Pompanic Street in the City of San Antonio. City of San Antonio utilities were also relocated for the roundabout.

Here is a cost breakout for construction of each of the three major portions of the construction project:

  • CR 52 milling and resurfacing (project 439832-1-52-01); $7.2 million.
  • CR 52 & College/Pompanic Roundabout (project 439832-3-52-01): $2.7 million
  • City of San Antonio Utility relocations for roundabout (project 439832-3-56-01): $280,500

_____________________________________
PROJECT UPDATE

Roundabout Now Open!

San Antonio / St. Leo – The new traffic roundabout on County Road 52 (CR 52) at the intersection of College Avenue and Pompanic Street opened to thru traffic on Friday, August 17, 2024.

Drivers should approach the roundabout with caution. Enter the roundabout going to the right and continue counterclockwise through the roundabout. Traffic entering the roundabout must yield to traffic already in the roundabout, but drivers should not stop if it is clear to enter. All turns onto connecting roads and continuing on CR 52 are right turns from the roundabout. The speed limit in the roundabout is 25 MPH.

Please remain alert to workers and equipment as construction continues in the roundabout area and along CR 52 to resurface the corridor from west of Storch Lane to US 98/US 301

_____________________________________
Modern Roundabout Safety and Navigation

  • Roundabouts are the Federal Highway Administration’s (FHWA)  leading action to reduce high-speed right-angle crashes and resulting fatalities. Roundabouts eliminate high-speed right-angle crashes at the intersection. Drivers are to travel at speeds less than 30 MPH and enter into the roundabout by merging.
  • The FHWA has conducted studies that demonstrate tremendous benefits of the roundabout design, including (1) Up to 90% reduction in fatalities; (2) 76% reduction in bodily injury cases; (3) 30-40% reduction in pedestrian crashes and (4) 75% fewer conflict points than four-way intersections.
  • This modern single-lane roundabout will be posted to be navigated at speeds of 25 MPH or less.

_______________________________________________
Click here to view the Virtual Public Meeting presentation about the roundabout portion of the project held on July 12, 2023.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • CR 52 at the Curley Street intersection
    Traffic controlled by law enforcement for signal work: 8 p.m. Thursday, January 23 to 5 a.m. Friday, January 24

Project Files
Project Videos
Project Images
Looking east over College Avenue at the roundabout (8-30-2024 photo)
Looking east over College Avenue at the roundabout (8-30-2024 photo)
An early morning view looking south from Pompanic Street (8-30-2024 photo)
Looking south over Pompanic Street at the new roundabout (8-30-2024 photo)
Looking southeast at the new roundabout at the CR 52 / College Avenue / Pompanic Street intersection (8-30-2024 photo)
Looking northeast from College Avenue at the new roundabout (8-30-2024 photo)
Looking northeast at the new roundabout from the College Avenue side (8-30-2024 photo)
Looking northwest at the roundabout that is now open to traffic (8-19-2024 photo)
Driving north on eastbound CR 52 into the roundabout (8-19-2024 photo)
Looking west on CR 52 towards the roundabout (8-19-2024 photo)
Looking west on CR 52 towards the roundabout (8-19-2024 photo)
Driving west on CR 52 into the roundabout (8-19-2024 photo)
Driving east on College Avenue going into the roundabout (8-19-2024 photo)
Looking south from Pompanic Street at the roundabout (8-19-2024 photo)
Looking southwest from Pompanic Street at the roundabout (8-19-2024 photo)
A pickup truck with a trailer easier navigates the roundabout (8-19-2024 photo)
Looking northwest at vehicles in the roundabout (8-19-2024 photo)
Traffic on College Avenue exiting and entering the roundabout (8-19-2024 photo)
A vehicle exits the roundabout onto eastbound CR 52 (8-19-2024 photo)
A driver exits the roundabout onto westbound CR 52 (8-19-2024 photo)
Looking southeast at roundabout construction at CR 52 / Pompanic Street / College Avenue (7/29/2024 photo)
Looking west over CR 52 at roundabout construction at the Pompanic Street (right) / College Ave. (top) intersection (7/29/2024 photo)
Looking south on CR 52 at crews placing concrete curb (7-18-2024 photo)
Looking west on CR 52 at crews placing concrete curb (7-18-2024 photo)
Crews work the concrete into curb and gutter form (7-18-2024 photo)
Crews work the concrete into curb and gutter form (7-18-2024 photo)
Crews work the concrete into curb and gutter form (7-18-2024 photo)
Crews work the concrete into curb and gutter form (7-18-2024 photo)
Crews work the concrete into curb and gutter form (7-18-2024 photo)
Working the concrete into curb and gutter shape (7-18-2024 photo)
Working the concrete into curb and gutter shape (7-18-2024 photo)
Curb and gutter taking shape (7-18-2024 photo)
Crews do concrete work along College Avenue (7-18-2024 photo)
Looking east along CR 52 from near the center of the new roundabout (7-18-2024 photo)
Looking north from CR 52 towards the center of the new roundabout (7-18-2024 photo)
Looking northwest at crews working on College Avenue (7-18-2024 photo)
Looking north at CR 52 roundabout construction (6-18-2024 photo)
Looking south on CR 52 at what will be the south leg of the roundabout (6-18-2024 photo)
Moving dirt in the CR 52 roundabout construction area (6-18-2024 photo)
Looking south from Pompanic Street at CR 52 roundabout construction (6-18-2024 photo)
Looking east from College Avenue at roundabout construction at the CR 52 intersection (6-18-2024 photo)
Looking at what will be the west leg of the new roundabout (College Avenue), west of CR 52 (6-18-2024 photo)
Looking northeast at closed CR 52, east of Pompanic Street (6-18-2024 photo)
Looking south where CR 52 is closed south of College Avenue for roundabout construction (6-18-2024 photo)
A truck travels from Pompanic Street onto College Avenue through the roundabout construction area (6-18-2024 photo)
Utility work on the east side Pompanic Street, just north of CR 52 (6-18-2024 photo)
Looking north from closed CR 52 to Pompanic Street at roundabout construction (6-18-2024 photo)
Paving on Pompanic Street, just north of CR 52 (5/24/2024 photo)
Paving on Pompanic Street, just north of CR 52 (5/24/2024 photo)
Reconstructing Pompanic Street north of CR 52 (5/20/2024 photo)
Looking northeast over CR 52 at construction on Pompanic Street (5/18/2024 photo)
Looking northwest over CR 52 at roundabout construction at Pompanic Street and College Avenue (5-18-2024 photo)
Looking northwest over CR 52 at roundabout construction at Pompanic Street and College Avenue (5-18-2024 photo)
Reconstructing Pompanic Street north of CR 52 (5/16/2024 photo)
Reconstructing Pompanic Street north of CR 52 (5/14/2024 photo)
Looking west at reconstructed College Avenue (4/25/2024 photo)
Looking west at reconstructed College Avenue (4/25/2024 photo)
Work on College Avenue for the west leg of the new roundabout (4/2/2024 photo)
Pompanic Street closed for roundabout construction from south of Pennsylvania Avenue to CR 52 (4/2/2024 photo)
Compacting roadway base on College Avenue (3/18/24 photo)
Work on College Avenue for the west leg of the new roundabout (2/15/2024 photo)
Work on College Avenue for the west leg of the new roundabout (2/15/2024 photo)
Work on College Avenue for the west leg of the new roundabout (2/15/2024 photo)