US 301 New Concrete Intersection at Gibsonton Dr & Repaving from Whitt Rd to Rivercrest Dr 443427-1-52-01
Project Details
Work Type | Resurfacing |
---|---|
Phase | Construction |
Limits | At Gibsonton Drive |
Project Start | January 6, 2025 |
City | |
County | |
Road | |
Construction Cost | $24.9 million |
Estimated Completion | Late 2025 |
Contractor | Ajax Paving Industries of Florida, LLC |
About
This project will replace the asphalt pavement with concrete at US 301 and Gibsonton Drive and repave the roadway from Whitt Road to Rivercrest Drive in Hillsborough County.
Once complete, the intersection improvement project will provide
- Two left-turn lanes from westbound Boyette Road onto southbound US 301
- Two through lanes from westbound Boyette Road across US 301
- One right-turn lane from westbound Boyette Road onto northbound US 301
This project is being constructed in conjunction with Financial Project Number 443426-1-52-01. For more information on that project, please click here.
Contact Information
Project Information |
---|
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
-
US 301 at Gibsonton Drive/Boyette Road
Lane closures: Monday, July 21 through Friday, July 25 nights from 9 p.m. to 7 a.m. -
US 301 at Gibsonton Drive/Boyette Road
Lane closures: Monday, July 14 through Friday, July 18 nights from 9 p.m. to 7 a.m.
US 301 from Whitt Rd to Rivercrest Drive
Lane closures: Monday, July 21 through Friday, July 25 nights from 9 p.m. to 7 a.m.