Project Details
Work Type Repaving
Phase Construction
Limits From west of SR 39 to west of Clarence Gordon Jr. Road
Project Start January 6, 2025
Length .9 miles
City
County
Road
Construction Cost $24.9 million
Estimated Completion Fall 2026
Contractor Ajax Paving Industries of Florida, LLC
About

The Florida Department of Transportation contractor is repaving SR 60 from west of SR 39 to west of Clarence Gordon Jr. Road in Hillsborough County.

In addition, this project is replacing the intersection's asphalt pavement with concrete at SR 60 and SR 39 and modifying two median openings on SR 60. These closures will improve safety and bring the road up to current access design standards along the corridor.

Construction activities are expected to finish during fall 2026.   

This project is being constructed in conjunction with Financial Project Number 443427-1-52-01. For more information on that project, please click here.

View Factsheet
Contact Information
Project Information
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • New Traffic Pattern on SR 60 in Plant City this Saturday

    Plant City, FL – Beginning Saturday, August 23, motorists should expect traffic on SR 60 to shift to the north side of the road from west of SR 39 to west of Clarence Gordon Jr. Road in Plant City.

    Over the next eight weeks, drivers may experience traffic delays and congestion on all nearby roads as crews build the new travel lanes along the south side of SR 60, weather permitting.

    Access for businesses, residents, and emergency vehicles is being maintained. Drivers are reminded to slow down, stay alert, and drive safely through the work zone.

    Improvements include the resurfacing of SR 60 from SR 39 to Clarence Gordon Jr. Road, replacing the asphalt pavement with concrete at the intersection of SR 39, and modifying the median openings on SR 60 to the east and west of SR 39 in Hillsborough County. Construction activities are expected to finish by fall of 2026.

    For more information on the SR 60 reconstruction project or to sign up for traffic alerts, visit FDOTTampaBay.com.

Project Files
Project Videos
Project Images
SR 60 Repaving from SR 39 to Clarence Gordon Jr Road (August 2025)
SR 60 Repaving from SR 39 to Clarence Gordon Jr Road (August 2025)
SR 60 Repaving from SR 39 to Clarence Gordon Jr Road (June 2025)
SR 60 Repaving from SR 39 to Clarence Gordon Jr Road (May 2025)